evidence, we conclude that the court’s determination of the existence of multiple
agreements was supported by substantial credible evidence.
[11] Link to KeyCite Notes ¶ 27 With regard to Weimar’s contention that, even if
there was a fixed price contract, the poor quality of Lyons’ work, which required
corrective measures, constituted a breach of the agreement, thereby excusing
here. I need these caps poured on the fountains right away.” And I told him that I
could see-with the radius walls and stuff, I could try to form that cap up but that it
was going to take a long time. And I was real busy and I told him that I didn’t
have time to do it. And he said his crew would do it. I said, “Well, if they could
form it up, we could come out and pour it.”
testified that Weimar told him to pour despite imminent rain and that Weimar had
stated “he would take responsibility,” with Berg likewise testifying that he
overhead Weimar tell Lyons to pour the concrete in the rain. The record
demonstrates that deficiencies found in the sidewalk were the result of pouring
the concrete in the rain. This continual rush to complete the project, even at the
agreements, the court weighed Weimar’s testimony about the appropriate
amount owed against Lyons’ testimony that he charged his regular, fair rate. “It is
well-established that the testimony of one witness is sufficient to prove any fact.”
Eustance v. State, 2005 MT 34, ¶ 11, 326 Mont. 77, ¶ 11, 107 P.3d 478, ¶ 11
(citations omitted). Moreover, “[i]n nonjury trials, the credibility of a witness and
the weight which his or her testimony should be afforded is within the sound
discretion of the district court. We will not reweigh the evidence and substitute
our judgment for that of the court under such circumstances.” In re Marriage of
Epperson, 2005 MT 46, ¶ 23, 326 Mont. 142, ¶ 23, 107 P.3d 1268, ¶ 23 (citations
omitted). Therefore, Lyons’ testimony, even if self-serving, was sufficient to