Critical path is A-B- F-G; completion time is 29 months. Variance of the critical
path is 3.02. Assuming a normal distribution, the probability of completion in 26
z = (27 – 29)/sqrt(3.02) = -1.15
Probability = 0.125. There is only a small chance of meeting this deadline.
Case Teaching Note: Alternative Water Supply – Single Project
Introduction
Gordon Rivers, the City Manager of Saratoga, Florida and Jay Andrews, the project
manager for Major Design Corporation (MDC), must manage this project. “We need the
‘intake and transmission main’ designed, bid, and completed in 35 weeks. The City of
Saratoga has a future $2 million dollar federal grant riding on the project getting done on
time,” Mr. Rivers said. Jay nodded in agreement. Mr. Rivers continued by saying, “Jay,
the project needs to come in on-schedule and within the budget. Now take this schedule
back and figure out how we are going to do it.” Notice that the case does not provide
how long the current project takes (which is 40 weeks). Therefore, the student needs to
do a basic CPM analysis and compute the total normal costs, critical path, activity slacks,
and current project completion time. Then they must crash the project from 40 to 35
weeks and eventually two paths become critical and require the crashing of both CPs.
Project Description
The objective of the project is to design a fully functional surface water intake that is
protective of the environment, will last at least 30 years, and will have a low life cycle
cost (i.e. capital, maintenance, and energy consumption). For this type of project,
engineering design accounts for 20 percent of total project cost. The design stage is also
important because the decisions made during design lock in 80 percent or more of the life
cycle costs of the project. The case describes each project activity and provides the data
below.
Alternative Water Supply (AWS) – Single Project