14. Developers under a plan approved by the city of Rye had constructed six luxury
cooperative apartment buildings and were to construct six more. To obtain certificates of
occupancy for the six completed buildings, the developers were required to post a bond
with the city to insure completion of the remaining buildings. The developers posted a
$100,000 bond upon which Public Service Mutual Insurance Company, as guarantor or
surety, agreed to pay $200 for each day after the contractual deadline that the remaining
buildings were not completed. After the contractual deadline, more than 500 days
passed without completion of the buildings. The city claims that its inspectors and
employees will be required to devote more time to the project than anticipated because it
has taken extra years to complete. It also claims that it will lose tax revenues for the
years the buildings are not completed. Should the city prevail in its suit against the
developers and the insurance company to recover $100,000 on the bond? Explain.
Answer: Liquidated Damages/Penalty Clause. No, the city will not prevail. Judgment for
the insurance company. A contract may contain a liquidated damage provision, but the
sum agreed upon must be a reasonable measure of the anticipated harm. Where,
15. Kerr Steamship Company sent a telegram at a cost of $26.78 to the Philippines through
the Radio Corporation of America. The telegram, which contained instructions in
unintelligible code for loading cargo on one of Kerr’s ships, was mislaid and never
delivered. Consequently, the ship was improperly loaded and the cargo was lost. Kerr
sued the Radio Corporation for the $6,675.29 in profits the company lost on the cargo
because of the Radio Corporation’s failure to deliver the telegram. Should Kerr be
allowed to recover damages from Radio? Explain.
Answer: Foreseeability and Damages. Judgment for Kerr in the amount of $26.78, the cost
of transmitting the telegram. The settled doctrine of this court confines the liability of a