tons of raisins, Sun Maid treated Victor’s repeated refusals to ship any more raisins as a
repudiation of the contract. In order to prevent breaching its own contracts, Sun Maid went into
the marketplace to “cover” and bought the raisins needed. Unfortunately, between the time
Victor refused delivery and Sun Maid entered the market, disastrous rains had caused the price of
raisins to skyrocket. May Sun Maid recover from Victor the difference between the contract price
and the market price before the end of the current crop year?
Answer: Anticipatory Repudiation. Sun Maid may bring suit immediately, and treat the anticipatory
17. In May, Watts was awarded a construction contract, based on its low bid, by the Cullman County
Commission. The contract provided that it would not become effective until approved by the state
director of the Farmers Home Administration (now part of the U.S. Department of Agriculture
Rural Development Office). In September, construction still had not been authorized and Watts
wrote to the County Commission requesting a 5 percent price increase to reflect seasonal and
inflationary price increases. The County Commission countered with an offer of 3.5 percent.
Watts then wrote the commission, insisting on a 5 percent increase and stating that if this was not
agreeable, it was withdrawing its original bid. The commission obtained another company to
perform the project, and on October 14, informed Watts that it had accepted the withdrawal of
the bid. Watts sued for breach of contract. Explain whether Watts will prevail and why or why
not.
18. K & G Construction Co. was the owner of and the general contractor for a housing subdivision
project. Harris contracted with the company to do excavating and earth-moving work on the
project. Certain provisions of the contract stated that (a) K & G was to make monthly progress
payments to Harris; (b) no such payments were to be made until Harris obtained liability
insurance; and (c) all of Harris’s work on the project must be performed in a workmanlike
manner. On August 9, a bulldozer operator, working for Harris, drove too close to one of K & G’s
houses, causing the collapse of a wall and other damage. When Harris and his insurance carrier
denied liability and refused to pay for the damage, K & G refused to make the August monthly
progress payment. Harris, nonetheless, continued to work on the project until mid-September,
when the excavator ceased its operations due to K & G’s refusal to make the progress payment. K
& G had another excavator finish the job at an added cost of 1,$450. It then sued Harris for the
bulldozer damage, alleging negligence, and for the $1,450 damages for breach of contract.
Harris claims that K & G defaulted first, having no legal right to refuse the August progress
payment. Did K & G default first? Explain.