any ficost increase” to be passed along to it. This worked well until fluctuations in the exchange
market caused the dollar to fall relative to the franc. By the time BSM changed the dollars
received from BD into francs to pay the Swiss manufacturer, the sale generated a much smaller
profit than anticipated. Fearing a further decline in the dollar, and relying on the open price
provision, BSM increased the price of the machines by 10 percent. BD sued, arguing that
fluctuations in the currency did not constitute a ficost increase” under the open price provision.
The court found for BD; BSM appealed.
Decision: Affirmed. Fluctuations in exchange rates do not constitute a valid increase in price
Force Majeure Clause—Force majeure is a French term meaning a fisuperior or irresistible
force.” It protects the contracting parties from problems or contingencies beyond their control.
Add. Case: Coker Intl. v. Burlington Ind. (4th Cir., 1991)–Coker agreed to buy 221 used textile
looms for $1 million from Burlington in December 1987. Coker gave Burlington a 10%
non-refundable payment. The balance was to be paid before removal of the looms before March
1. If the looms were not removed, Burlington had the right to sell the looms to others. The
contract contained a force majeure clause (to protect the parties in event of an occurrence
beyond their control): fiDeliveries may be suspended by either party in case of act of God, war,
riots, fire, explosion, flood, strike, lockout, injunction, inability to obtain fuel, power, raw
materials, labor, containers, or transportation facilities, accident, breakage of machinery or
apparatus, national defense requirements or any cause beyond the control of such party,
preventing the manufacture, shipment, acceptance, or consumption of a shipment of the Goods
or of a material upon which the manufacturer of the Goods is dependent.”
Coker intended to sell the looms to customers in Peru, but no looms were picked up or paid for
by the deadline. On May 27 Coker told Burlington that payment and removal of the looms would
take place by June 30 as it needed an import license to Peru and a letter of credit from the buyer.
Burlington agreed to the June 30 extension, but warned Coker it would be the last. By July 6,
payment had not been received, so Burlington put the looms up for sale. Coker had taken
delivery of 34 of the looms and paid a total of $239,750. Coker demanded the return of the down
payment and referred to the force majeure provision. Its customer in Peru could not accept
delivery for reasons beyond Coker’s control. Coker sued. The court held for Burlington. Coker
appealed.
Decision: Affirmed. fiCoker … argued that its contractual obligations should be discharged due
to the intervening cancellation on all import licenses by the government of Peru. It further
argued that since the type of used looms it agreed to purchase are only marketable in developing
countries, it could not reasonably make other disposition.” The court disagreed, finding:
1) fiFirst, the language of the contract expressly states that the down payment is non-refundable
2) fiSales to developing countries are inherently risky, especially in Latin America and South
America. Thus, the nonoccurrence of political turbulence resulting in economic uncertainty for