Smaller firms have difficulty establishing a reputation, especially in international markets. To
provide quality assurance, the Intl. Org. for Standardization (ISO) coordinates standards in many
areas of business. Its certification is evidence that a firm is capable of quality products in
particular areas.
Add. Case: In re Earle Industries (E.D., Pa., 1988)–CE ordered some custom-made equipment
from Earle for $17,800. Earle said it normally took ten weeks. November 18, CE placed the
order, telling Earle it needed the equipment in early January. Earle responded that the
equipment would be ready the end of January but that delivery was on a “best efforts” basis.
When the equipment was not ready the end of January, CE cancelled the order. Earle billed CE
for $4,000 to cover costs to date that could not be recovered. CE contended it owed nothing due
to breach of contract.
Decision: CE will pay $4,000. The contract did not set a firm delivery date of the end of
Add. Case: Baker v. DEC Corp. (Sup. Ct., Mich., 1998–Plaintiffs, dairy farmers, contracted to
buy a DEC milking machine. Equipment was delivered to local dealer at the end of July, was
installed at the farm on Sept. 8, and was tested and approved for operation by the Department of
Agriculture on Sept. 12. On Sept. 10, four years later, plaintiffs sued DEC for breach of
warranty, claiming the equipment was defective and injured their operation. DEC countered that
the four-year statute of limitation had expired before suit was filed. Trial court agreed with
DEC; court of appeals reversed; DEC appealed.
Decision: Reversed. Tender of delivery, for purposes of statute of limitations for breach of sales
contract did not occur until seller offered conforming goods. The manufacturer had no
Add. Case: Allsopp Sand & Gravel v. Lincoln Sand & Gravel (App.Ct., Ill., 1988)–In March,
“Allsopp agreed to supply and Lincoln agreed to purchase 50,000 tons of FA-1 specification
sand for $1.20 per ton. … Lincoln agreed to pay the balance due under the contract by
December 31 … and to take delivery of the remaining tonnage of sand by the spring….” Sand
was to be loaded during regular business hours; “loading out at other times was to be by
‘special arrangements.’” Lincoln took and paid for a quarter of the sand. In December, owing
$45,000 by the end of the month, Lincoln requested it get the rest of the sand. Allsopp said the pit
was closed and to reopen it before next spring the price would be raised 20 or 25 cents per ton;
Lincoln offered 5 cents more and to have its employees help with loading; Allsopp refused and
sued for payment.
Decision: “The dispositive issue on review is whether Allsopp’s refusal to make special
arrangements to load out sand in December at the original contract price was commercially
reasonable.” “First, we must determine whether a price increase is inherent in the term special
arrangements. A contract for goods will not be held invalid for indefiniteness just because