no substitutions have been made since the time of delivery.
8. What is the purpose of a pre-inspection?
9. What is the purpose of an initial inspection?
10. What is a prefinal inspection, and when is it conducted?
1. What quality control organization do you recommend the contractor use on the
NanoEngineering Building?
2. What are mock-ups the general contractor should require subcontractors to construct for
the NanoEngineering Building?
5. List out five examples each of ‘active’ and five examples of ‘passive’ quality control
Active: Sub pre-qualifications, Sub short-lists, Project Specific QC plans from