2. Below is a revised accelerated
delivery schedule that meets both objectives: 1. delivery of the first plane
2 weeks (10 working days) ahead of schedule, and 2. at the least
incremental cost to Coastal.
Increment
ABG
ABC
All of the paths need to be evaluated when reducing a project’s
completion time. However, the selection of activities to crash should be
taken from the critical path first and then the activities should be selected
in order according to the smallest crash cost. The critical path ABGEFJK
(65 days) is reduced to 55 days; however, the critical path changes as a
3. The total incremental costs Bob
Peterson will have to pay for this revised accelerated delivery schedule