CHAPTER 14
14-2 Early starts and late starts create havoc for BCWS because a percentage of the
allocated budget may already show up as spent when, in fact, the work has not
yet begun.
14-3 Line managers will “pad” their estimates in order to protect themselves.
14-4 The management reserve should be used on high-risk activities, and only
when needed. Otherwise, there may not be any use for the management
reserve.
14-6
Cumulative Cost
(in thousands)
Variance $
Week
BCWS
BCWP
ACWP
Schedule
EAC %
1
50
50
25
0
50
2
70
60
40
(10)
66.6
3
90
80
67
(10)
83.7
4
120
105
90
(15)
85.7
5
130
120
115
(10)
95.8
6
140
135
130
(5)
96.3
7
165
150
155
(15)
100.3
8
200
175
190
(25)
108.6
9
250
220
230
(30)
104.5
10
270
260
270
(10)
103.8
11
300
295
305
(5)
103.4
12
350
340
340
(10)
100.0
13
380
360
370
(20)
102.8
14
420
395
400
(25)
101.3
15
460
460
450
0
97.8
Project Management Instructor’s Manual 20 Chapter 14
14-8 (a) 1840 hours per year or 153.33 hrs/month