CHAPTER 14
14-2 Early starts and late starts create havoc for BCWS because a percentage of the
allocated budget may already show up as spent when, in fact, the work has not
yet begun.
14-3 Line managers will “pad” their estimates in order to protect themselves.
14-4 The management reserve should be used on high-risk activities, and only
when needed. Otherwise, there may not be any use for the management
reserve.
14-6
Cumulative Cost
(in thousands)
Project Management Instructor’s Manual 20 Chapter 14
14-8 (a) 1840 hours per year or 153.33 hrs/month