Insert your answers into the gray-shaded cells or select from drop-down
list. If an answer is incorrect, the word “wrong” will appear.
Did Promotional Products complete the 180 units by 5 P.M.?
Cum. Dept. 2 backlog – – 5 6 6
Although Dept. 1 averaged 45 units per hour, it was late getting 6 units to Dept.
2 in the last two hours. Since the robot was constrained to 45 units per hour, it
could not handle the extra 5 units given it between 3:00 and 4:00 and the extra 1
unit given it between 4:00 and 5:00.