5 – 3
3. A contractor is planning to use a hydraulic excavator to remove the soil for the construction of
the foundation for a new hotel. He has determined from the project plans that 3,000 bank cubic
yards must be excavated and that 817 compacted cubic yards will be required to backfill the
completed foundation. The contractor plans to stockpile the soil needed for backfill on site and
haul the excess soil off site using dump trucks that have a heaped capacity of 30 loose cubic yards.
The contractor had the soil tested and determined that the bank density is 2,800 pounds per cubic
yard, the loose density is 2,295 pounds per cubic yard, and the compacted density is 3,256 pounds
per cubic yard.
a. What is the percent swell for the soil?
𝑐𝑢.𝑓𝑡.−2,295 𝑙𝑏𝑠
𝑐𝑢.𝑓𝑡.)(100%)
𝑐𝑢.𝑓𝑡.=22%
b. What is the percent shrinkage for the soil after being compacted?
c. How many bank cubic yards should be stockpiled to be used for the backfill operation?
d. How many truckloads of excess material should be hauled off site, if the trucks are fully loaded
to their heaped capacity?