Process Technology Equipment Chapter 7 Compressors
23. Which of the following is a step in the typical start-up procedures for a
compressor?
A. Close all block valves.
B. De-energize all equipment.
C. Depressurize the compressor.
D. Drain any liquid from the compressor’s case.
24. Which of the following is a step in the typical lockout/tagout procedure for a
compressor?
A. Depressurize the compressor.
B. Use an inert gas to purge the compressor case of air.
C. Place ancillary lubricating and seal oil systems into operation.
D. Drain the compressor’s case or cylinders to remove any liquid.