Unlock access to all the studying documents.
View Full Document
PROBLEMS
Developing Learning Curves
1. Mass Balance Company
Time for the second unit
Time for the first unit
48
60
0.8
r=
=
=
( )
( )
1
40
0.321928
log log 2
log 0.80 log 2
0.321928
60 40
18.30 hr
b
n
br
k k n
k−
=
=
=−
=
=
=
c. Estimated total time for 40 units, from Table I.1, conversion factor = 0.42984.
d. Estimated total time for 30 units, from Table I.1, conversion factor = 0.46733.
( )
( )
( )
1
0.1047
5
0.1047
10
0.1047
15
0.1047
30
log log 2
log 0.93 log 2 0.1047
85 5
71.82 hr
66.79 hr
85 15
64.02 hr
85 30
59.53 hr
b
n
br
k k n
k
k
k
−
−
−
−
=
= = −
=
=
=
=
=
=
=
=
Using Learning Curves
3. A large grocery corporation
The first unit required 30 hours.
. We can use Table I.1 and straight-line
interpolation to get the cumulative average time factor for a 90 percent learning
curve. The following solution was developed with the use of a computer routine.
The production schedule is not feasible because the number of employees needed in
week 4 exceeds the maximum of 40 by 6 workers.
To obtain a feasible schedule, we can produce some of the requirements in week 4
earlier, say in week 2 or 3. Such a change may result in excess inventory cost if the
customer does not accept early shipment. Furthermore, the production schedule of
other products may be affected by this alternative.
One possible production schedule is:
Week
Scheduled
Production
Total Hr
Hr/Wk
Employees/Wk
2
85
105
1,817
1,381
35
3
100
205
3,216
1,399
35
4
120
325
4,758
1,542
39
5
120
445
6,261
1,503
38
a. From Table I.1, 80 percent learning curve, n = 64,
b. Week of Friday the 13th
5. Bovine Products Company. We know the time required for the 16th unit. We need to
use a 90% learning curve and work backwards to estimate the time for the 1st unit.
(1)
(2)
(1) (2)
Cumulative
Cumulative
Cumulative
Hours/
Scheduled
Production
Avg. Factor
Total Hr
Order
First order
16
16
0.75249
275.23
Second order
48
64
0.62043
907.71
log log2
log0.90 log2 0.152
br
b
=
= = −
( )
( )( )
0.322
3
40 0.80
50
log 0.80
log 0.322
log2 log2
50 3
35.10 hours
r
r
b
k−
==
= = = −
=
=
( )( )
0.322
100 50 100
11.35 hours
k−
=
=
c. Average time per unit over a total order of 1000 units (using factor from Table I.1
for r = 80% and n = 1,000, (50)(0.15867) = 7.93 hours. The contract’s assumption
is valid.
7. Powerwest Inc.
a. Direct hours for the thirtieth unit
k k n
br
k
k
nb
n
n
=
= = ( ) =−= −
=( )
=
−
1
0152
09
004576
30 000 13
20 314
log
log .
.
,
,
.
hours
b. Total hours for 30 units. From Table I.1 90% learning curve, conversion factor for
c. By inspection the maximum number of employees will occur sometime during the
first four months. Because of the learning effect, production following April
cannot possibly exceed the hours required for April. For example, the four units in
August require about 9,500 fewer hours than do the four units in April.
(1)
Cumulative
Production
(2)
Cumulative
Avg. Factor
(1) (2)
Cumulative
Total Hr
The maximum number of employees is
d. If the learning curve is changed to 0.85, we cannot use Table I.1 to find the
cumulative average factor. We have used a spreadsheet to generate the cumulative
average factor for a learning rate of 85%.
(1)
Cumulative
Production
(2)
Cumulative
Avg. Factor
(1) (2)
Cumulative
Total Hr
The maximum number of employees is
or 355 employees
8. Really Big Six Corporation
Cost to buy = $2,000
9. When the learning curve is 80%
log log2
log0.80 log2 0.322
br
b
=
= = −
( )
( )
( )
( )
( )
( )
11
1
0.322
0.322
1
3.10559 1
10.005
10.005
1 0.005
0.995 1
0.995 1
0.995 1
1.0156887 1
0.0156887 1
1
0.0156887
63.74 or 64
b
b
b
b
b
b
b
bb
b
b
k n k n
kn
nn
n
n n n
nn
nn
nn
nn
n
n
n
−
−
−
−+
=
−+ =
− + =
=+
=+
=+
=+
=
=
=
hours, n = 64, and learning curve is 80%.
hours and the estimated learning curve rate from part a,
( )( )
( )
0.28252466
80
80
46 80
13.338 hours
k
k
−
=
=
11. Hand-To-Mouth Company
Poor cash management is the number one cause of bankruptcy. The following
spreadsheet shows the calculation of cash flow. HTM must not take this order unless
they are assured they can obtain a loan to cover the cash shortages occurring in weeks
8–10. Some of the values for the cumulative average hours factor were interpolated
from data in Table I.1. Tabular values below may have slight rounding-off errors.