3. Developing the Project Schedule
Once the project network is complete, project managers can find the critical path, identify start
and finish times for each activity to build a project schedule, and calculate slack time for each
activity.
1. Critical path defined:
2. Project schedule
• Earliest start time (ES)
• Earliest finish time (EF)
EF = ES + t
• Latest start time (LS)
LS = LF – t
• Latest finish time (LF)
LF = Earliest of the [LS times for all immediately following activities]
3. Activity slack and Gantt charts
4. Activity slack: maximum time an activity can be delayed without delaying the entire project
• Total slack = LS – ES or LF – EF.
• Critical path
5. Application 7.2, continuing Application 7.1
Calculate the four times for each activitity in order to determine the critical path and project
duration.