16 CHAPTER 3 PRO J E C T MA N A G E M E N T
12. The critical path is the shortest time possible for the completion
13. Dummy activities have no time duration. They are inserted
14. They are (1) optimistic time (a), an estimate of the minimum
time an activity will require; (2) most likely time (m), an estimate of
15. No. In networks, there is no possibility that crashing a non-
critical task can reduce the project duration. Only critical tasks
17. Slack: the amount of time an activity can be delayed and not
affect the overall completion time of the whole project. Slack can
18. If there are a sufficient number of tasks along the critical path,
sum of the variances of all activities on the critical path.
normal distribution.
20. Waterfall approach: the project progresses smoothly, in a
projects run so late and so overbudget?
Students are expected to read about such projects and come
This protects the organization from a total loss should the massive
project never be completed.
1. Both A and H are critical activities. Describe the difference
between what happens on the graph when you increase A vs.
2. Activity F is not critical. By how many weeks can you in-
3. Activity B is not critical. By how many weeks can you in-
4. What happens when you increase B by 1 more week after it