Chapter 05 – Cost Estimation
5-6
• When past data are used, the relevant range for the projection is usually between the
upper and lower bounds of past activity levels for which data are available.
• Past data may be the only readily available, cost–effective basis for estimating costs. As
long as their limitations are recognized, past data can be a meaningful starting point.
• A scattergraph is a graph that plots costs against activity levels. This visual
representation of the data provides a quick indication of the fixed-variable relation of
costs and activities. It also indicates if the relation seems to change at certain activity
levels. Exhibit 5.2 shows the data and a scattergraph for a service center.
• The number of observations needed for scattergraph depends on the availability of the
data, the variability within the data, the relative costs and benefits of collecting reliable
data, and the length of time the current process has been in operation.
• A common rule of thumb is to use three years of monthly data if the physical processes
have not changed significantly within that time. If the operations have changed
significantly, data that predate the change may be misleading. Stable cost and activity
levels require a shorter time period (and fewer observations).
• A line can be visually fitted (by way of “eyeball judgment”) to the data points as closely
as possible and extended to the vertical axis on the scattergraph.
• The slope of the line represents the estimated variable cost per unit (i.e., the increase in
variable costs associated with an increase of one unit of activity), and the intercept with
the vertical axis represents an estimate of the fixed cost.
• When there are no observations of cost behavior around the zero activity level, the data
do not indicate the costs that would be incurred when the activity level was zero. In this
case, the interpretation of the intercept as the fixed cost will no longer be valid.
• An estimate on the basis of a scattergraph is subject to a high level of error, especially if
the points are scattered widely.
• Scattergraphs are usually used to illustrate the relations between costs and activity and
to point out any past data items that might be significantly out of line, but not the sole
basis for cost estimates.
♦ High-low cost estimation is a method to estimate costs based on two cost observations on the
scattergraph, usually at the highest and lowest activity levels.
• Activity can be defined in terms of units of production, hours of work, or any other
measure that makes sense for the problem at hand.