Chapter 17 – Project Management
Step 2:
The paths and their expected duration are shown below:
Rank critical activities according to crash costs:
Activity L should be shortened 1 week because it has the lowest crashing cost ($125) on Path
K-L-M-Q-P-Z, which will decrease Paths K-L-M-Q-P-Z & K-L-M-Q-Y 1 week as shown
below.
Activity N should be shortened 1 week because it has the lowest crashing cost ($45) on Path
K-N-J-Q-P-Z, which will decrease Paths K-N-J-Q-P-Z & K-N-J–Q-Y 1 week as shown
below.
Combined crashing cost = $170. This cost is ≤ $375.
Activities crashed to this point: Step 1: Activity Z (1st week). Step 2: Activity L (1st week) &
Activity N (1st week).