Chapter 17 – Project Management
A summary of the crashing steps is shown below:
Length
after
crashing 1
week
Length
after
crashing 2
weeks
Length
after
crashing 3
weeks
Length
after
crashing 4
weeks
Length
after
crashing 5
weeks
Length
after
crashing 6
weeks
1-2-5-7-11-13
1-3-8-11-13
1-3-9-12-13
1-4-6-10-12-13
Activity Cost
7-11 $20
6-10 $ 5
$25
Activity Cost
11-13 $30
4-6 $ 8
$38
Activity Cost
11-13 $33
1-4 $10
$43
Activity Cost
1-2 $22
1-3 $12
6-10 $12
$46
Conclusion: Expected project duration = 29 weeks (shortened by 6 weeks).
Total crashing cost = $15 + $18 + $25 + $38 + $43 + $46 = $185.
Total indirect costs = 29 x $40 = $1,160.
Total cost over 29 weeks = $185 + $1,160 = $1,345(000) = $1,345,000
The table below summarizes the cumulative crashing cost, indirect cost, and total cost for
project lengths of 35, 34, 33, 32, 31, 30, and 29 weeks:
Cumulative
Weeks
Shortened
Cumulative
Crash Cost
($000)