17–14
Education.
6. The network diagram is given in Problem 1, Part a. After 12 weeks, activities 1-2, 1-3, and 2-4
have been finished; activity 2-5 is 75% finished; and activity 3-6 is 50% finished. How many
weeks after the original start date time should the project be finished. The original path expected
durations are given below:
One way of solving this problem is to look at the effects on each path:
Path 1-2-4-7-10-12:
Activities 1-2 and 2-4 were estimated to require take 4 + 9 = 13 weeks. They finished in 12
weeks. In other words, Activity 2-4 finished 1 week early. The net effect is to reduce the expected
time of this path by 1 week to 22 weeks.
Path 1-2-5-8-10-12:
Activities 1-2 and 2-5 were estimated to require 4 + 8 = 12 weeks. Activity 2-5 is 75%
completed; therefore, 50% of the activity time (.50 * 6 = 3 weeks) remains. This means that this
activity should be completed 1 week early because it should be completed by the end of week 15.
The net effect is to reduce the expected time of this path by 1 week to 30 weeks.