Chapter 16 – Scheduling
16–51
Education.
(d) Job E has the shortest time (4). Because the time for Job E is at Deburring, schedule
Job E toward the end of the sequence (5th). Eliminate Job E from further
consideration.
1st 2nd 3rd 4th 5th 6th 7th
1st 2nd 3rd 4th 5th 6th 7th
Chapter 16 – Scheduling
16–52
The Grinding flow time is 107 hours, which is 14 hours greater than the flow time for the
SPT sequence (107 – 93 = 14).
The total time (makespan) is 35 hours, which is 2 hours shorter than the SPT makespan (37 –
35 = 2).
d. The tradeoff is between shorter flow time in the Grinding department and shorter total time
(makespan). The production manager would be indifferent concerning the sequences when
the increase in flow time at the Grinding department = the decrease in total time (makespan).
16–53
Education.
15. Given:
We have the following set of jobs in the order of their arrival:
Remaining
Number of
Operations
a. Determine the processing sequence using (1) FCFS, (2) SPT, (3) EDD, and (4) CR. For each
sequence, computer the average tardiness, the average flow time, and the average number of
jobs at the work center:
(1) FCFS Sequence: a-b-c-d-e-f
����� �� ������
Initial critical ratios at day 0:
Critical Ratio Calculation
Job a is scheduled first.
Chapter 16 – Scheduling
At day 0 + 4.5 = 4.5 [Job a completed], the critical ratios are:
Critical Ratio Calculation
Job c is scheduled next.
Critical Ratio Calculation
Job b is scheduled next.
Critical Ratio Calculation
Job e is scheduled next.
Chapter 16 – Scheduling
16–55
Education.
At day 15.7 + 2.8 = 18.5 [Job e completed], the critical ratios are:
Critical Ratio Calculation
Job f is scheduled next.
Only Job d remains. Job d is scheduled last.
CR Sequence: a-c-b-e-f-d
Performance Measures for each Rule
Chapter 16 – Scheduling
Education.
Average job flow time = Total job flow time / Number of jobs
b. Using the results from part a, show that the average flow time and the average number of jobs
measures are equivalent for all four sequencing rules:
There are several ways to show this. One is to calculate the ratio of average flow time to
average number of jobs for each rule and then observe that they are equal. Here the ratios are
equal to 3.90.
Chapter 16 – Scheduling
16–57
Education.
c. Determine the processing sequence using the S/O rule:
Slack = Time until due date – Remaining time to process
Slack per operation (S/O) = Slack / Number of remaining operations
Slack per
Operation
(S/O)
Chapter 16 – Scheduling
16–58
16. Given:
Remaining
Processing
Time
(days)
Remaining
Number of
Operations
Slack per operation (S/O) = Slack / Number of remaining operations
Slack per
Operation (S/O)
Chapter 16 – Scheduling
At hour 2.5+ 3.5 = 6 [Job a completed], the critical ratios are:
Critical Ratio Calculation
Job b is scheduled next.
At hour 6 + 2.0 = 8 [Job b completed], the critical ratios are:
Critical Ratio Calculation
At hour 8 + 6.0 = 14 [Job f completed], the critical ratios are:
Critical Ratio Calculation
Job c is scheduled next.
Only Job d remains. Job d is scheduled last.
CR sequence: e-a-b-f-c-d