16–33
Education.
10. Given:
The times required to complete each of 8 jobs in a two-machine flow shop are shown in the table
below. Each job must follow the same sequence, beginning with Machine A and moving to
Machine B.
a. Determine a sequence that will minimize makespan time:
We will use Johnson’s rule to sequence the jobs. The Johnson’s rule steps from the text are
shown below:
1. Select the job with the shortest time. If the shortest time is at the first work center,
2. Eliminate the job and its time from further consideration.
3. Repeat steps 1 and 2, working toward the center of the sequence, until all jobs have been
scheduled.
(a) Job e has the shortest time (2). Because the time is at Machine A, schedule Job e first
(1st). Eliminate Job e from further consideration.
1st 2nd 3rd 4th 5th 6th 7th 8th