978-0078024108 Chapter 11 Part 5

subject Type Homework Help
subject Pages 7
subject Words 1063
subject Authors William J Stevenson

Unlock document.

This document is partially blurred.
Unlock all pages and 1 million more documents.
Get Access
page-pf1
Chapter 11 - Aggregate Planning and Master Scheduling
11-41
Education.
Step 4: Compare the costs of Option 1 (keep the same number of employees, produce 1,400 units
per month using regular time, and produce 100 units total using overtime) vs. Option 2 (hire 1
Option 1: Maintain 28 employees & produce 100 units total using overtime in equal
amounts in Months 1- 5:
Period
1
2
3
4
5
6
Forecast
1,500
1,400
900
1,200
1,500
1,700
Output
Regular
1,400
1,400
1,400
1,400
1,400
1,400
Part Time
Overtime
20
20
20
20
20
Subcontract
Output - Forecast
-80
20
520
220
-80
-300
Inventory
Beginning
0
0
0
460
680
600
Ending
0
0
460
680
600
300
Average
0
0
230
570
640
450
Backlog
80
60
0
0
0
0
Costs:
Regular
@
5
$7,000
$7,000
$7,000
$7,000
$7,000
$7,000
Part Time
@
$0
$0
$0
$0
$0
$0
Overtime
@
7.5
$150
$150
$150
$150
$150
$0
Subcontract
@
$0
$0
$0
$0
$0
$0
Hire/Layoff
Inventory
@
1
$0
$0
$230
$570
$640
$450
Back orders
@
6
$480
$360
$0
$0
$0
$0
Total
$7,630
$7,510
$7,380
$7,720
$7,790
$7,450
Conclusion: Total cost using overtime = $45,480.
page-pf2
Chapter 11 - Aggregate Planning and Master Scheduling
11-42
Education.
Option 2: Hire 1 worker & produce 1,417 units every month using regular time:
Period
1
2
3
4
5
6
Total
Forecast
1,500
1,400
900
1,200
1,500
1,700
8,200
Output
Regular
1,417
1,417
1,417
1,417
1,417
1,417
8,502
Part Time
0
Overtime
0
Subcontract
0
Output - Forecast
-83
17
517
217
-83
-283
302
Inventory
Beginning
0
0
451
668
585
Ending
0
0
451
668
585
302
Average
0
0
226
560
627
444
1,855
Backlog
83
66
0
0
0
0
149
Costs:
Regular
@
5
$7,085
$7,085
$7,085
$7,085
$7,085
$7,085
$42,510
Part Time
@
$0
$0
$0
$0
$0
$0
$0
Overtime
@
7.50
$0
$0
$0
$0
$0
$0
$0
Subcontract
@
$0
$0
$0
$0
$0
$0
$0
Hire/Layoff
$0
Inventory
@
1
$0
$0
$226
$560
$627
$444
$1,855
Back orders
@
6
$498
$396
$0
$0
$0
$0
$894
Total
$7,583
$7,481
$7,311
$7,645
$7,712
$7,529
$45,259
page-pf3
Chapter 11 - Aggregate Planning and Master Scheduling
11-43
Education.
19. Given:
Use the industrial pumps information from Figure 11.11:
June
July
1
2
3
4
5
6
7
8
Forecast
30
30
30
30
40
40
40
40
Customer
Orders
33
20
10
4
2
The calculations for MPS and projected on-hand inventory are shown below:
Week
Inventory From
Previous Week
Requirements*
Net
Inventory
before
MPS
(70)
MPS
Projected
On-hand
Inventory
1
64
33
31
31
2
31
30
1
70
71
3
71
30
41
41
4
41
30
11
11
5
11
40
29
70
41
6
41
40
1
70
71
7
71
40
31
31
8
31
40
9
70
61
requirements + Current week’s MPS.
Note: We need a MPS quantity whenever Net Inventory before MPS < 10 units.
Example calculations for projected on-hand inventory:
Week 1:
Net Inventory before MPS = 64 33 = 31. No MPS is needed.
Projected on-hand inventory = 31 + 0 = 31.
Week 2:
The final MPS is shown below:
page-pf4
Chapter 11 - Aggregate Planning and Master Scheduling
11-44
Education.
Beg. Inv. = 64
June
July
1
2
3
4
5
6
7
8
Forecast
30
30
30
30
40
40
40
40
Customer
Orders
33
20
10
4
2
Projected on-
hand
inventory
31
71
41
11
41
71
31
61
MPS
70
70
70
70
ATP
31
36
68
70
70
ATP (first period) = Beginning inventory + MPS (first period) sum of customer
orders until (but not including) the period of the next MPS.
ATP (other periods) = MPS (current period) sum of customer orders until (but
not including) the period of the next MPS.
*We calculate ATP in the first period and in all other periods with MPS
quantities.
ATP (Week 1) = 64 + 0 (33) = 31
ATP (Week 2) = 70 (20 + 10 + 4) = 36
page-pf5
Chapter 11 - Aggregate Planning and Master Scheduling
11-45
Education.
20. Given:
Update the information from Figure 11.11:
It is now the end of Week 1. Customer orders are 25 for Week 2, 16 for Week 3, 11 for Week 4, 8
for Week 5, and 3 for Week 6. Use the MPS rule of ordering when project on-hand inventory
would be negative without production.
June
July
2
3
4
5
6
7
8
Forecast
30
30
30
40
40
40
40
Customer
Orders
25
16
11
8
3
Beginning inventory = projected on-hand for Week 1 from Figure 11.11 = 31 units
Lot size = 70 units
The calculations for MPS and projected on-hand inventory are shown below:
Week
Inventory From
Previous Week
Requirements*
Net
Inventory
before
MPS
(70)
MPS
Projected
On-hand
Inventory
2
31
30
1
1
3
1
30
-29
70
41
4
41
30
11
11
5
11
40
-29
70
41
6
41
40
1
1
7
1
40
-39
70
31
8
31
40
-9
70
61
*Requirements equal the larger of forecast and customer orders in each week.
Net Inventory before MPS = Inventory from previous week Current week’s
requirements.
Projected on-hand inventory = Inventory from previous week Current week’s
requirements + Current week’s MPS.
Note: We need a MPS quantity whenever Net Inventory before MPS < 0 units (i.e.,
when it is negative).
Example calculations for projected on-hand inventory:
Week 2:
Net Inventory before MPS = 31 30 = 1. No MPS is needed.
Projected on-hand inventory = 1 + 0 = 1.
Week 3:
The final MPS for Weeks 2 8 is shown below:
page-pf6
Chapter 11 - Aggregate Planning and Master Scheduling
11-46
Education.
June
July
Beg. Inv. = 31
2
3
4
5
6
7
8
Forecast
30
30
30
40
40
40
40
Customer
Orders
25
16
11
8
3
Projected on-
hand
inventory
1
41
11
41
1
31
61
MPS
70
70
70
70
ATP
6
43
59
70
70
ATP (first period) = Beginning inventory + MPS (first period) sum of customer
orders until (but not including) the period of the next MPS.
ATP (other periods) = MPS (current period) sum of customer orders until (but
not including) the period of the next MPS.
*We calculate ATP in the first period and in all other periods with MPS
quantities.
ATP (Week 2) = 31 + 0 (25) = 6
page-pf7
Chapter 11 - Aggregate Planning and Master Scheduling
11-47
21. Given:
We have the following forecasts and customer orders over the next eight weeks:
1
2
3
4
5
6
7
8
Forecast
50
50
50
50
50
50
50
50
Customer
Orders
52
35
20
12
The calculations for MPS and projected on-hand inventory are shown below:
Week
Inventory From
Previous Week
Requirements*
Net
Inventory
before
MPS
(75)
MPS
Projected
On-hand
Inventory
1
0
52
-52
75
23
2
23
50
-27
75
48
3
48
50
-2
75
73
4
73
50
23
23
5
23
50
-27
75
48
6
48
50
-2
75
73
7
73
50
23
23
8
23
50
-27
75
48
*Requirements equal the larger of forecast and customer orders in each week.
Net Inventory before MPS = Inventory from previous week Current week’s
requirements.
Projected on-hand inventory = Inventory from previous week Current week’s
requirements + Current week’s MPS.
Note: We need a MPS quantity whenever Net Inventory before MPS < 0 units (i.e.,
when it would be negative).
Example calculations for projected on-hand inventory:
Week 1:
Net Inventory before MPS = 0 52 = -52. Warning: This is below the desired level of 0
units. We must plan for 75 units of MPS.
Projected on-hand inventory = -52 + 75 = 23.
Week 2:
Net Inventory before MPS = 23 50 = -27. Warning: This is below the desired level of
The final MPS is shown below:

Trusted by Thousands of
Students

Here are what students say about us.

Copyright ©2022 All rights reserved. | CoursePaper is not sponsored or endorsed by any college or university.