Exercise 22-16 (25 minutes)
1.
Ornamental Sculptures Mfg.
Direct Materials Budget
For the Months of March and April
March April
Budgeted production (units) 3,300 4,600
Materials requirements per unit x 8 x 8
*April: 20% x 36,800 = 7,360 lbs.
May: 20% x 38,400 = 7,680 lbs.
2.
Ornamental Sculptures Mfg.
Direct Labor Budget
For the Months of March and April
March April
Budgeted production (units) 3,300 4,600
3.
Ornamental Sculptures Mfg.
Factory Overhead Budget
For the Months of March and April
March April
Total direct labor hours needed 1,650 2,300
VOH rate per DL hour x $3 x $3