Chapter 15 – Operational Performance Measurement: Indirect-Cost Variances and Resource-Capacity Management
15-35 Traditional ABC Costing (50 minutes)
Standard MH per unit = 32,000 MH 6,400 units = 5 MH per unit
No. of units manufactured during the period = standard allowed MH standard
MH/unit = 30,000 MH 5 MH/unit = 6,000 units
Budgeted no. of units/setup = 6,400 units 32 set-ups = 200 units/set-up
Standard no. of setups for the units manufactured = 6,000 200 = 30
FB based on Inputs FB based on Outputs
(i.e., based on actual (i.e., based on standard
1. Actual activity units) allowed activity units)
VOH:
Setup 28 × $600 = $ 16,800 30 × $600 = $ 18,000
Total Flexible-Budget Variance
= $48,000U
FB based on Inputs FB Based on Outputs
(i.e., on actual (i.e., based on standard
2. Actual activity units) allowed activity units)
VOH:
Setup 28 × $2,600 = $ 72,800 30 × $2,600 = $ 78,000
MH 35,000 × $5 = 175,000 30,000 × $5 = 150,000
FOH: 200,000 200,000
Total OH $480,000 $447,800 $428,000