– – – – line indicates slack indicates activity schedule
A
0
2
0
2
0
critical
B
0
4
3
7
3
C
2
6
2
6
0
critical
D
2
7
4
9
2
c. Slack = 2 for activity D
6. a. Completion time of the project = 9
b. The critical path is B – D – G
7. a.
b. The expected project completion time is E(T) = 31.664
Critical path is A-B-C-D-F
8. a.
9. a.
10. a. The T.A. should perform activity D to reduce the project completion time by one day.
The cost will be the total cost for the project plus $150 for crashing activity D by one day.
The project completion time is 8 days.
b. Now there are two critical paths (B-D-G) and also (C-G), both are 8 days long. To
c. Slack = 2 for activity D
6. a. Completion time of the project = 9
b. The critical path is B – D – G
7. a.
b. The expected project completion time is E(T) = 31.664
Critical path is A-B-C-D-F
8. a.
9. a.
10. a. The T.A. should perform activity D to reduce the project completion time by one day.
The cost will be the total cost for the project plus $150 for crashing activity D by one day.
The project completion time is 8 days.
b. Now there are two critical paths (B-D-G) and also (C-G), both are 8 days long. To