___________________ uses the planned orders generated by MRP to evaluate the
feasibility of long-term or blanket contracts and to determine delivery need.
Consider a workstation that can process 4 units per minute. It takes 10 minutes to
receive an order from the previous station. The container size is 10 units. The factory
sets safety stock at 20 percent of demand during lead time. How many kanbans are
needed for the workstation?
Suppose that a plant manager is only evaluated based on the partial productivity
measure: output/(number of employees). If she replaces 10% of the workforce with
robots (one robot per replaced worker), and output remains the same, what will be the
percent change in this measure of productivity?