In making a forward pass through a network, three activities are immediate
predecessors for activity T. What is the early start time for activity T?
a) the smallest ES for the three activities that are immediate predecessors for activity T
b) the largest ES for the three activities that are immediate predecessors for activity T
c) the smallest EF for the three activities that are immediate predecessors for activity T
d) the largest EF for the three activities that are immediate predecessors for activity T
e) the activity time for activity T
Companies use ____________ to check that enough work is scheduled for operations
and that the amount of work scheduled is feasible.
a) capacity management
b) closed-loop requirements planning
c) cut requirements planning
d) capacity resources planning
e) capacity requirements planning
What are the two major decisions to be made when using the periodic review system?