A work center has five jobs assigned to it. They are labeled, in the order of their arrival
in the shop, as jobs A, B, C, D and E. The work center may work on only one job at a
time and must complete any job it starts before starting another job. Job A has a
processing time of 6 days and is due to the customer in 9 days. Job B has a processing
time of 2 days and is due in 16 days. Job C has a processing time of 4 days and is due in
10 days. Job D has a processing time of 3 days and is due in 7 days. Job E has a
processing time of 5 days and is due in 12 days. Using the shortest operating time
priority rule, in what order should these jobs be undertaken?
Answer: