You are working on a project that has 12 activities and want to perform a CPM analysis
on the project. You determine the critical path consists of only five activities. You then
compute the variances for the five critical path activities and these variances are 3, 4, 2,
1 and 6 days. If the desired completion date for the project is 50 days and the expected
completion date for the project is 40 days, what is the probability that the project will be
completed by the desired completion date?
A.0.99379
B.0.99180
C.0.99772
D.0.91924
E.0.67364
Answer:
Which of the following best describes the term cycle time?
A.Average time between completions of successive units
B.Ratio of the time a resource is activated over its use
C.Can be no more that 60 minutes
D.The same as utilization
E.The labor content of the item being measured
Answer: