(A) the activities which are on the critical path
(B) the expected project duration
(C) the probability that the project will be completed in 29 weeks or less
27) A productivity increase in one operation that does not improve overall productivity
of the business is not
A.worthwhile.
B.trivial.
C.competence-destroying.
D.an order winner.
E.an order qualifier.
28) A company produces two products (A and B) using three resources (I, II, and III).
Each product A requires 1 unit of resource I and 3 units of resource II and has a profit of
$1. Each product B requires 2 units of resource I, 3 units of resource II, and 4 units of
resource III and has a profit of $3. Resource I is constrained to 40 units maximum per
day; resource II, 90 units; and resource III, 60 units.
What is the objective function?
29) A work sampling study of dockworkers must be set up. There will be a large
number of random observations. However, for this exercise, determine an observation
schedule (arranged chronologically) for six observations. Assume workers are on the
docks for eight hours a day, and that the study will be done over a 60-day period. Use
the random digits listed below.