A simple CPM network has three activities, D, E, and F. D is an immediate predecessor
of E and of F. E is an immediate predecessor of F. The activity durations are D=4, E=3,
F=8.
A) The critical path is D-E-F, duration 15.
B) The critical path is D-F, duration 12.
C) Slack at D is 3 units.
D) Slack at E is 3 units.
E) Both A and C are true.
A manager must decide on the mix of products to produce for the coming week.
Product A requires three minutes per unit for molding, two minutes per unit for
painting, and one minute for packing. Product B requires two minutes per unit for
molding, four minutes for painting, and three minutes per unit for packing. There will
be 600 minutes available for molding, 600 minutes for painting, and 420 minutes for
packing. Both products have contributions of $1.50 per unit. Answer the following
questions; base your work on the solution panel provided.