Answer:
You have just been assigned to oversee a series of projects. Functional areas will loan
you personnel for each project and separate project managers will be responsible for
separate projects. These project managers will report to you. Which project
management structure is being used?
A.Pure Project
B.Task force
C.Matrix Project
D.Functional Project
E.PERT
Answer:
You have been called in as a consultant to set up a Kanban control system. The first
thing to do is to determine the number of Kanban card sets needed. Your research shows
that the expected demand during lead time for a particular component is 1,200 per hour.
You estimate the safety stock should be set at 5% of the demand during lead time. The
tote trays used as containers can hold 2 units of stock and the lead time to replenish an
order is 10 hours. Which of the following is the number of Kanban card sets necessary
to support this situation?
A.5,000
B.5,500
C.6,300