A print shop has four jobs that have to be processed through their only five-color press.
They usually use the first come, first served (FCFS) rule of scheduling jobs. However,
the customers are waiting in the lobby for these jobs so the shop wants to minimize the
average waiting time. They are going to use the shortest processing time rule to do so.
Processing times for each job are as follows (assume this is the arrival order): Job A, 30
minutes; Job B, 17 minutes; Job C, 12 minutes; and Job D, 39 minutes.
Using the shortest processing time (SPT) rule to sequence these jobs, the average
waiting (flow) time is _____.
a. less than or equal to 20 minutes
b. more than 20 but less than or equal to 30 minutes
c. more than 30 but less than or equal to 40 minutes
d. more than 40 but less than or equal to 50 minutes
Answer:
It is time for a company to do its MRP schedule, but they aren’t sure which lot sizing
approach to use: lot-for-lot (LFL), fixed-order quantity (FOQ) using the EOQ approach,
or periodic-order quantity (POQ). They have the following information regarding the
product they wish to produce:
Carrying costs = $1 per unit per week
Setup costs = $125
Annual demand = 2000 units
Work year = 50 weeks
a. What is the production lot size for Week 2 using the LFL method?