You have run a capacity resource profile on your shop. Products have been routed
sequentially through resources A, B, C, and D. The capacity resource profile tells you
that resource A is scheduled at 95 percent of capacity, resource B at 80 percent of
capacity, resource C at 130 percent of capacity, and resource D at 100 percent of
capacity. Assuming that the data we used to calculate the capacity resource profile are
accurate, what would we expect to find when we go out to the shop?
________________________________________________________.
What are “project milestones?” _________________________________________