A manufacturer of cat towers wishes to locate a super assembly facility to meet their cat
tower assembly needs for the next millennium. Currently, carpet, cylinders, yarn and
fasteners are purchased in bulk from suppliers in North Haverbrook, Ogden, and
Springfield in the quantities shown in the table. The super assembly facility would ship
to distribution centers located in Seattle, Lubbock, Nashville, and Philadelphia. The
locations of all of these cities on an x-y grid, outbound transportation costs on a ton per
mile basis, and total tonnage are all contained in the table.
What is the cost to transport 500 tons of material between the Springfield and Seattle