by the four stages A to D below. This process could be human resource management,
marketing, accounting, finance, or engineering process, and Steve is the manager. This
is his chance to impress his boss and get promoted again. After three months on the job,
Steve realizes something is not right with the process. His employees experience big
pile up of work, things take too long to be processed, the opportunity for error is
increasing, and the entire process is almost chaotic. Do a process and capacity analysis
of this process. The numbers in parenthesis(#) are the time inminutes to complete one
unit of work. Demand on the process averages 30 units per hour and each unit must be
worked on by all four stages. Administrative clerk(s) do Stage A work. The assistant
manager(s) are cross-trained to do both Stages C and D work. The coding specialist(s)
do Stage B work.
The total process (throughput) capacityin units per hour for the four-stage process A
to D assuming 3 administrative clerks, 3 coding specialist, and 3 assistant managers on
duty is:
a. less than 10 units per hour.
b. more than 10 units but less than or equal to 20 units.
c. more than 20 units but less than or equal to 30 units.
d. more than 30 units but less than or equal to 40 units.
Answer: