The latest start (LS) time for activity D is
a. 8 days.
b. 11 days.
c. 19 days.
d. 12 days.
Strategies for proactive demand management would not include
a. shifting demand into other time periods.
b. offering products or services with countercyclical demand patterns.
c. partnering with suppliers to reduce information distortion along the supply chain.
d. using subcontracting to meet unexpected high demand levels.
Consider an espresso stand with a single barista. Customers arrive at the stand at the
rate of 28 per hour according to a Poisson distribution. Service times are exponentially
distributed with a service rate of 35 customers per hour. The average number of
customers waiting in line for service is
a. 4.0
b. 3.8