predecessors for activity T, which has an activity time of 7. The early start times for
activities L, M, and P are 22, 17, and 27, respectively. The early finish times for
activities L, M, and P are 29, 27, and 33, respectively. What is the early finish time for
activity T?
a) 17
b) 24
c) 27
d) 33
e) 40