15) Attempting to determine when preventive maintenance activities should be
performed is called:
A.breakdown maintenance.
B.forecastive maintenance.
C.preventive maintenance.
D.predictive maintenance.
E.corrective maintenance.
16) A lot can be “accepted” or “rejected” in a multiple-sampling plan:
A.after one sample is taken.
B.after two samples are taken.
C.after three or more samples are taken.
D.all of the choices.
E.none of the choices.
17) The quality manager for Frozen Pizzas, Inc., is concerned about the quality of the
lot of several thousand pizzas which his company produced this week, and is now ready
to ship. If he uses an acceptance sampling plan of n = 8 and c = 1, what is the
probability that, if this lot is 10 percent defective, it will be accepted for shipment
without inspection?
A..9619
B..9428
C..8131
D..4305
E..1869
18) A lean-systems method of asking questions about a process is the __________