A simple CPM network has three activities, A, B, and C. A is an immediate predecessor
of B and of C. B is an immediate predecessor of C. The activity durations are A=4,
B=3, C=8.
A) The critical path is A-B-C, duration 15.
B) The critical path is A-C, duration 12.
C) The critical path is A-B-C, duration 13.5
D) The critical path cannot be determined without knowing PERT expected activity
times.
E) The network has no critical path.
Which one of the following does not exemplify JIT used for competitive advantage?
A) Acme Foods decides to decrease the number of its suppliers to just a few.
B) Ajax, Inc. is proud to announce that incoming goods are delivered directly to the
point of use.
C) Ardoyne Builders has a scheduled preventive maintenance program.
D) Cheramie Trucking trains workers to specialize and become very efficient in one
job.
E) Cajun Contractors has reduced the amount of space for inventory.
What describes a system that stores and displays information that can be linked to a