Here are the data for a time-cost CPM scheduling model analysis. The time is in days
and the costs include both direct and indirect costs
.
What are the total time of this project and total normal cost?
A. Total time is 13 days, total cost is $1,200.
B. Total time is 12 days, total cost is $1,700.
C. Total time is 11 days, total cost is $1,600.
D. Total time is 10 days, total cost is $1,750.
E. Total time is 9 days, total cost is $1,700.
Which of the following is the net requirement using an MRP program if the gross