20) Given the following information, what would utilization be?
Effective capacity = 20 units per day
Design capacity = 60 units per day
Actual output = 15 units per day
A.1/4
B.1/3
C.1/2
D.3/4
E.none of these
21) A methods and measurements analyst for Digital Devices needs to develop a time
standard for the task of assembling a computer mouse. In a preliminary study, she
observed one of her workers perform this task six times with the following results:
What is the observed time for this task?
A.34 seconds
B.40 seconds
C.46 seconds
D.48 seconds
E.240 seconds
22) A quality analyst wants to construct a sample mean chart for controlling a
packaging process. He knows from past experience that whenever this process is under
control, package weight is normally distributed with a mean of 20 ounces and a
standard deviation of two ounces. Each day last week, he randomly selected four
packages and weighed each:
If he uses upper and lower control limits of 22 and 18 ounces, on what day(s), if any,
does this process appear to be out of control?
A.Monday
B.Tuesday
C.Monday and Tuesday