Assume you are sequencing a job using Johnson’s rule. The job requires 7 hours to
assemble and then is followed by 8 hours in the painting department. Which of the
following is where you would schedule this job?
A.As early as possible in the unfilled job sequence
B.As late as possible in the unfilled job sequence
C.The schedule would depend on the due date
D.Does not matter
E.Johnson’s Rule does not apply
Answer:
With which of the following should we use an “X-bar” chart based on sample means to
monitor process quality?
A.Grades in a freshman “pass/fail” course
B.Tire pressures in an auto assembly plant
C.Vehicles passing emissions inspection
D.Computer software errors
E.Number of units with missing operations
Answer: