Quick search
Join
Home
>
Quiz
>
Mathematics Chapter 9 Give the expected project completion date and the critical
Sidebar
Close
Mathematics Chapter 9 Give the expected project completion date and the critical
0
Helpful
0
Unhelpful
August 11, 2022
Related documents
Econ 120 Practice Test Answers
Chapter 1 Business And Its Environment
Sociology
Wow My Love
Case Report Laquinta
Article Review: Administrators and Accountability: The Plurality of Value Systems in the Public Domain
FC 42957
FC 62472
FIN 91396
FE 34842
Unlock access to all the studying documents.
View Full Document
Chapter 9 – Project Scheduling: PERT/C
PM
Activity
Optimistic
Most
Probable
Pessimistic
A
2
5
6
B
1
3
7
C
6
7
10
D
5
12
14
E
3
4
5
F
8
9
12
G
4
6
8
H
3
6
8
I
5
7
12
J
12
13
14
K
1
3
4
a.
What are the critical path activities?
b.
What
is
the expected time
to
complete
the project?
c.
What
is
the probability the proj
ect will take more than
28
days
to
complete?
a.
and
b.
Expected Time
Chapter 9 – Project Scheduling: PERT/C
PM
52.
The critical path for this network
is
A – E
– F and the project completion
time
is
22
weeks.
Activity
Normal
Time
Crash
Time
Normal
Cost
Crash
Cost
A
12
8
8,000
12,000
B
14
10
5,000
7,500
C
8
8
10,000
10,000
D
5
3
6,000
8,000
E
4
3
5,000
7,000
F
6
5
9,000
12,000
G
10
8
5,000
8,000
If
a deadline
of
17
weeks
is
imposed, give th
e linear programming model fo
r the crashing decision.
Chapter 9 – Project Scheduling: PERT/C
PM
53.
For the project represented below, determine
the earliest and latest start and
finish times for
each
activity
as
well
as
t
he
expected overall completion time.
Activity
Duration
ES
EF
LS
LF
Slack
A
4
B
3
C
4
D
2
E
5
F
2
G
5
H
6
[F,
9,
11, 10,
12,
1]; [G, 12,
17,
12,
17,
0]; [H,
9,
15, 11, 17,
2]
Determining the critical path
54.
Consider the following PERT/CPM
network with estimated times
in
weeks.
The project
is
scheduled
to
begin
on
May
1.
Crashing activity times
Chapter 9 – Project Scheduling: PERT/C
PM
The three-time estimate approach
was
used
to
calculate the exp
ected times and the following
table gives the variance for
each
activity:
Activity
Variance
Activity
Variance
A
1.1
E
0.3
B
0.5
F
0.6
C
1.2
G
0.6
D
0.8
H
1.0
a.
Give the expected project completion
date and the critical path.
b.
By
what date are
you
99%
sure the project will
be
completed?
a.
16
weeks = Aug.
21
b.
About Sept.
22
(20.66
weeks from May
1)
Variability
in
project completion
time
55.
A project consists
of
five activities. Naturally the pain
t mixing precedes the pain
ting activities. Also, both ceiling
painting and floor sanding must
be
done
prior
to
floor buffing.
Optimistic
Most Probable
Pessimistic
Activity
Time (hr)
Time (hr)
Time (hr)
Floor sanding
3
4
5
Floor buffing
1
2
3
Paint mixing
0.5
1
1.5
Wall painting
1
2
9
Ceiling painting
1
5.5
7
a.
Construct the PERT/CPM netwo
rk for this problem.
b.
What
is
the expected completion
time
of
this project?
c.
What
is
the probability that the
project
can
be
completed within 9
hr.?
c.
.8264
Chapter 9 – Project Scheduling: PERT/C
PM
TOPICS:
Variability
in
project completion
time
56.
Consider a project that has been modeled
as
follows:
Activity
Immediate Predecessors
Duration (hr)
A
—
7
B
—
10
C
A
4
D
A
30
E
A
7
F
B,C
12
G
B,C
15
H
E,F
11
I
E,F
25
J
E,F
6
K
D,H
21
L
G,J
25
a.
Draw the PERT/CPM network
for this project and determine project’s exp
ected completion
time and
its
critical path.
b.
Can activities E and G
be
performed sim
ultaneously without delaying
the minimum project
completion time?
c.
Can
one
person perform
A,
G,
and
I without delaying the project?
d.
By
how
much
can
activities G and L
be
delayed
without delaying the entire pr
oject?
e.
How much would
the project
be
delayed
if
activity G
was
delayed
by
7 hours and activity L
was
delayed
by
4 hours? Explain.
Expected Completion Time =
58;
Critical Path
= A – D – K
b.
Yes
c.
Yes
d.
Slack
on
G = 7 hours; Slack
on
L = 4 hours
e.
4 hours; the slack times are
not
independent
as
G and L are
on
the same path.
POINTS:
TOPICS:
Determining the critical path
57.
Joseph King has ambitions
to
be
mayor
of
Williston, Nort
h Dakota. Joe has determined the
breakdown
of
the steps
to
the nomination and has estimated no
rmal and crash costs and times
for the campaign
as
follo
ws (times are
in
weeks).
Normal
Crash
Im
mediate
Activity
Time
Cost
Time
Cost
Predecessors
A.
Solicit Volunteers
6
$5,000
4
$
9,000
—
Chapter 9 – Project Scheduling: PERT/C
PM
B.
Initial “Free” Exposure
3
$4,000
3
$
4,000
—
C.
Raise Money
9
$4,000
6
$10,000
A
D.
Organize Schedule
4
$1,000
2
$
2,000
A
E.
Hire Advertising Firm
2
$1,500
1
$
2,000
B
F.
Arrange
TV
Interview
3
$4,000
1
$
8,000
B
G.
Advertising Campaign
5
$7,000
4
$12,000
C,
E
H.
Personal Campaigning
7
$8,000
5
$20,000
D,
F
Joe King
is
not a wealthy
man
and would like
to
organize a
16
-week
campaign
at
minimum cost. Writ
e and solve a linear
program
to
accomplish this task.
Chapter 9 – Project Scheduling: PERT/C
PM
58.
Marcy Fetter, a staff analyst
at
th
e Los Angeles plant
of
Computer Produ
cts Corporation,
is
assigned
to
the team that
is
developing the process design
for producing
an
RFID sensor. The corporate planning
group
in
San Jose, California has
contacted her and has asked
how
confident the desig
n group
is
about completing the pr
oject
in
60
days. She has
developed these estimated time duratio
ns
in
days for the project:
Activity
Immediate
Predecessor
Activities
Optimistic
Time (
t
o
)
Most Likely
Time (
t
m
)
Pessimistic
Time (
t
p
)
A
—
10
12
15
B
A
6
10
14
C
A
10
15
20
D
A
9
9
18
E
B
5
6
8
F
C,E
10
12
13
G
B
12
14
16
H
B,D
18
21
24
I
B,D
10
15
20
J
F.G.H
8
10
14
a.
Compute the expected time and
variance for
each
a
ctivity.
b.
Determine the critical path and th
e expected duration
of
the project.
c.
What
is
the probability
that the project will take longer than
58
days
to
complete?
d.
Which path
in
the project network offers the gr
eatest risk
of
overrunning
a new deadline
of
56
days?
Chapter 9 – Project Scheduling: PERT/C
PM
59.
A project has the following activiti
es, precedence relationships,
and time estimates
in
weeks:
Activity
Immediate
Predecessor
Activities
Optimistic
Time (
t
o
)
Most Likely
Time (
t
m
)
Pessimistic
Time (
t
p
)
A
—
15
20
25
B
—
8
10
12
C
A
25
30
40
D
B
15
15
15
Chapter 9 – Project Scheduling: PERT/C
PM
E
B
22
25
27
F
E
15
20
22
G
D
20
20
22
a.
Compute the expected time and
variance for
each
a
ctivity.
b.
Determine the critical path and th
e expected duration
of
the project.
c.
What
is
the probability
that the project will take longer than
56
weeks
to
complete?
60.
Three paths
of
a PERT network hav
e these
mean
durations and
variances
in
weeks:
Path
Mean
Duration
Variance
1
45
2.75
2
44
5.50
3
46
1.20
Which path offers the greatest risk
of
overrunning a contract deadline
of
48
weeks?
Chapter 9 – Project Scheduling: PERT/C
PM
61.
A project has the following activiti
es, durations, costs, and
precedence relationships:
Activity
Present Duration
(Weeks)
Accelerated
Duration
(Weeks)
Immediate
Predecessor
Activities
Present
Cost
Accelerated
Cost
A
10
9
—
$11,000
$15,000
B
15
13
—
20,000
25,000
C
10
6
A
9,000
20,000
D
20
18
A
25,000
30,000
E
15
10
C
20,000
35,000
F
17
15
B
20,000
30,000
G
12
10
B
15,000
25,000
H
9
8
D,F
12,000
18,000
I
7
6
G,H
10,000
15,000
Develop a cost-time trade-off analy
sis. Detail the steps that
you
would use
to
accelerate
or
crash the project
to
its
minimum duration
at
the
lowest cost. Determine each step’s cost an
d the duration
of
the project.
A
D
G
H
Chapter 9 – Project Scheduling: PERT/C
PM
62.
National Oil Company (NATOCO)
must plan the shutdown
of
its
Houston refinery for routine preventive
maintenance. Each
hour
of
downtime
is
lost production
time and
is
very costly,
so
NATOCO wants the maintenance
project completed
in
22
hours. The PERT network
below shows the precedence relation
ships
of
the activities involved
in
the project. The table gives the
act
ivity
times and costs under no
rmal operations and maximum crashing.
NATOCO wants
to
know the minimum
cost
of
completing the maintenance pr
oject within the
22
-hour period.
Formulate
and solve a linear program that will
yield this information.
Act
ivity
Normal
Time (hr)
Normal
Cost
Crash
Time (hr)
Crash
Cost
A
2
$2,000
1.5
$3,000
B
4
3,000
3
3,500
C
1
1,500
1
1,500
D
4
5,300
2.5
8,000
E
6
5,400
5
7,000
F
10
6,000
8
9,000
G
8
4,800
5
9,900
H
2
2,800
1
2,900
I
5
4,500
4
5,000
J
12
6,000
6
9,600
K
7
7,000
4
9,700
L
11
8,800
9
9,200
M
4
1,000
1
7,000
Chapter 9 – Project Scheduling: PERT/C
PM
Chapter 9 – Project Scheduling: PERT/C
PM
Essay
Chapter 9 – Project Scheduling: PERT/C
PM
63.
Name
at
least three managerial situation
s where answers are provided
by
project management solutions.
64.
Explain how and why all predecessor
activities must
be
considered when fin
ding the earliest start time.
65.
Explain how and why all successor activities
must
be
considered when finding th
e latest finish time.
66.
Once the earliest and latest times are calculated,
how
is
the critic
al path determined?
67.
Why should projects
be
monitored after the critic
al path
is
found?
68.
Suppose that, after analyzing a pr
oject network, the project manager fin
ds the project duration
unacceptable. Discuss the op
tions the manager might have fo
r reducing the duration.