25) The bank manager of a busy downtown location found herself unable to find good teller help
so she invested in an ATM to handle the routine withdrawals that tended to occupy an inordinate
amount the teller’s time. Before she installed the ATM she found that customers were arriving on
average every 2 minutes (Poisson distributed) and it took a teller 30 seconds (exponentially
distributed) to process their request. The ATM is able to maintain a constant 30 second service
time. What is the impact on the number of customers waiting in line?
A) There is no change.
B) The ATM line is half as long as the teller line.
C) The ATM line is twice as long as the teller line.
D) The ATM line is 25% shorter than the teller line.
26) The bank manager of a busy downtown location found herself unable to find good teller help
so she invested in an ATM to handle the routine withdrawals that tended to occupy an inordinate
amount the teller’s time. Before she installed the ATM she found that customers were arriving on
average every 60 seconds (Poisson distributed) and it took a teller 20 seconds (exponentially
distributed) to process their request. The ATM is able to maintain a constant 30 second service
time. What is the impact on the waiting time for the customers?
A) There is no change.
B) The wait in the ATM line is 50% shorter than the wait in the teller line.
C) The wait in the ATM line is 50% higher than the wait in the teller line.
D) The wait in the ATM line is 25% shorter than the teller line.