72
12
. Which of the following statements is best?
a
. the largest element of manufacturing lead time is queue
b
. the larger the load, the longer the queue
c
. if queue is reduced, the lead time and work in process will be reduced
d
. all of the above are true
13
. A scheduling system in which the last operation on a routing is scheduled first and for
completion on the due date is called:
a
. forward scheduling
b
. backward scheduling
c
. infinite scheduling
d
. finite scheduling
14
. A scheduling system that assumes the required capacity will always be available is called:
a
. forward scheduling
b
. backward scheduling
c
. infinite scheduling
d
. finite scheduling
15
. Which of the following statements is best?
a
. implementation is achieved by issuing a shop order to manufacturing
b. engineering drawings, bills of material and routings may be included in a shop
packet
c
. the dispatch list is the instrument of priority control
d
. all of the above are true
16
. Which of the following are methods of reducing manufacturing lead time?
I. Subcontracting
II. Forward scheduling
III. Operation overlapping
IV. Operation splitting
a
. all of the above
b
. I and II
c
. II and III
d
. II and III
e
. III and IV
17
. Operation overlapping means:
a
. the same job running on two machines at the same time
b
. using alternate routings
c
. moving work to the next operation as a group of pieces is completed
d
. running two or more jobs at the same time
e
. locating work centers close together to reduce materials handling
18
. Which of the following statements is best?
a
. a bottleneck (capacity constraint resource) will control the throughput of all
products processed by it
b
. a time buffer should be established before a bottleneck
c
. work centers feeding a bottleneck should work at full capacity