10) Refer to the scenario above. The manager assigns tasks to workstations and breaks ties using
a longest operation heuristic. That is, if two or three tasks could be assigned to a given station,
the manager assigns the longest task first and then fills in the remaining time at the workstation
as completely as possible. Using this approach, what task(s) would be assigned at the fourth
station?
A) N, P
B) M
C) N, O
D) O, P
Use this scenario for the following questions.
The process design team at a manufacturer has broken an assembly process into eight basic steps,
each with a required time, and predecessor as shown in the table. There are 7.5 productive hours
available in a day and the manufacturer wishes to produce 400 units. Balance the line by
assigning tasks to workstations to fill up as much takt time as possible. Break ties by assigning
the longest task first.
11) Refer to the scenario above. What task(s) should be assigned at the third workstation?
A) B and E
B) D
C) C, E, and G
D) F