6) Which of the following statements regarding time-cost tradeoffs in CPM networks is false?
A) Crashing shortens project duration by assigning more resources to critical tasks.
B) Crashing sometimes has the reverse result of lengthening the project duration.
C) Crashing must consider the impact of crashing an activity on all paths in the network.
D) Activities not on the critical path can become critical after crashing takes place.
E) A negative crash cost per period would imply that either crashing is cheaper than not crashing or that
the crash time was slower than the normal time.
7) If an activity whose normal duration is 13 days can be shortened to 10 days for an added cost of $1,500,
what is the crash cost per period?
A) $500
B) $1,500
C) $750
D) $13,000
E) $15,000
8) Two critical path activities are candidates for crashing on a CPM network. Activity details are in the
table below. To cut one day from the project’s duration, activity ________ should be crashed first, adding
________ to project cost.
A) One; $400
B) One; $6,800
C) Two; $1,000
D) Two; $5,000
E) One or Two should be crashed; $1,400