8) A simple CPM network has three activities, D, E, and F. D is an immediate predecessor of E and of F. E
is an immediate predecessor of F. The activity durations are D=4, E=3, F=8.
A) The critical path is D-E-F, duration 15.
B) The critical path is D-F, duration 12.
C) Slack at D is 3 periods.
D) Slack at E is 3 periods.
E) Both A and C are true.
9) Activity D on a CPM network has predecessors B and C, and has successor F. D has duration 6. B’s
earliest finish is 18, while C’s is 20. F’s late start is 26. Which of the following is definitely true?
A) B is a critical activity.
B) C is completed before B.
C) D has no slack but is not critical.
D) D is critical, and has zero slack.
E) F is critical, and has zero slack.
10) Which of the following statements regarding CPM networks is true?
A) There can be multiple critical paths on the same project, all with different durations.
B) The early finish of an activity is the latest early start of all preceding activities.
C) The late start of an activity is its late finish plus its duration.
D) If a specific project has multiple critical paths, all of them will have the same duration.
E) None of the above are true.