(M) 7. _____ source contracting is when there exists only one supplier in the market-place to
satisfy the requirements of the contract.
(E) 8. Companies that give part of a procurement contract to multiple suppliers do so to:
(E) 9. Which of the following is not one of the three types of specifications discussed in the
text?
(M) 10. For long-term projects, such as weapon systems projects, contracted for by the
Department of Defense, the type of contract can change from life cycle phase to life
cycle phase.
(M) 11. Which of the following is generally not part of “Conducting the Procurements”?
(E) 12. The cost of renting a piece of equipment is $200 per day and the leasing cost is $5000
plus $100 per day. The breakeven cost between renting and leasing occurs at _____
days.